The art of living upscale atMansionThe Rivus – Elie Saab Editionis increasingly clearly visible, as the entire key utility system and internal landscape enter the final stage of completion.
Items are 100% completed
- Clubhouse & accompanying amenities: BBQ area, basketball court, children’s playground, central park and community amenities have been completed and ready for trial operation.
- 31 villas in SAVA subdivision: Complete the entire exterior architecture, ready for the handover phase.
- Critical infrastructure: Lift bridge, internal roads (phase 1 & 2), Phuoc Thien street connecting the outside area and central park infrastructure have all been completed.
- Internal lift bridge: has been tested, ready for use, marking an important completion step in the internal transport network.
Progress of landscape & internal amenities
- Green landscape: continues to be upgraded, increasing the density of greening throughout the area, creating a sustainable and highly aesthetic ecosystem.
- Riverfront park: 98% of landscape infrastructure has been completed; Paving, lighting and greenery system reached nearly 96%, currently refining the final details.
- Boat lock and river bed: main technical items completed, entering phasetest operationbefore being officially put into operation.
Progress of villa subdivisions
- Stage 2:Complete 99% of the exterior architecture, prepare for handover of auxiliary items.
- Stage 3:Achieving 95% of the architectural volume, 96% of the landscape infrastructure is completed with a system of green trees, paving stones and synchronous internal traffic.
The Rivus is gradually taking on its complete appearance – placeClubhouse iconis ready to open its doors to residents, andGreen area along the riverEvery detail is being taken care of.
Each architectural block, each internal route reflects the spirit of “Haute Couture Living – The ultimate art of living“, shaping the living standards of the future elite community in Thu Duc.










Saigon LuxuryWill continue to update images and videosThe latest actual progress of The Rivus– when the entire The Rivus area officially entered the first phase of handover.