Latest progress update December 12

Cập nhật tiến độ hoàn thiện mới nhất The Global City

With the continuous efforts of the Masterise Homes team and partners, by the end of December 12, The Global City urban area constantly changing new look. SOHO TOWNHOUSE RAPIDLY COMPLETES OUTSIDE AND INTERNAL PARK READY FOR HANDOVER

  • SOHO Townhouse Area: Exterior finishing work is being accelerated, currently 85% of the overall progress has been completed. The road between the townhouses has been paved and sidewalks are being installed. In addition, the park at SOHO is also being deployed. The construction atmosphere at SOHO is also much more bustling to meet the handover schedule for customers.
  • City Park – The largest amusement park in the new Center: continues to complete the tree planting items, game area, sports center, etc. In addition, the most modern Go-kart racetrack in Southeast Asia at City Park has just completed the construction of the running track, preparing to install game items.

Especially, during the festival month of December 12, New Center The Global City continuously become the venue for a series of large-scale events

  • International event AI Day with many interesting technology projects debuting for the first time
  • The event series “Unlocking Investment Opportunities” with the topic of investment potential for educational real estate development in the SOHO townhouse area, received much attention from businesses and investors.
  • Fashion exhibition week by Harper’s Bazaar magazine brings together hundreds of businessmen, artists, and celebrities
  • Indispensable, the New Year’s Eve festival Luxury Countdown Party attracts more than 50.000 city residents to have fun, watch fireworks combined with water music.

Check out the latest progress photos of the new The Global City center.

Contact PKD Saigon Luxury Company

  • Phone: 0918.195.449 Ms. Nhi
  • Consulting and project address: THE GLOBAL CITY, An Phu Ward, (District 2), Thu Duc City, Ho Chi Minh City