As of early February 2025, construction of The Rivus luxury villa community continues to progress steadily, maintaining rigorous quality standards and adhering to the planned schedule. With a commitment to professional execution and accountability, the Masterise Homes team and partners are dedicated to delivering a premium living environment for future residents. Below is an overview of The Rivus construction progress:
? 31 villas in the SAVA district: 100% exterior architecture complete and ready for resident occupancy.
? Remaining villas: 95% of Phase 2 exterior architecture completed and 75% of Phase 3 completed.
? Lifting bridge: Over 98% of construction completed with continued testing operations throughout January 2025.
? Children’s park: 100% hardscape and landscaping completed, providing a safe and verdant recreational space for children.
? Central park: 90% hardscape and landscaping completed with ongoing tree planting to enhance the residents’ recreational space.
? Riverside park: 90% hardscape completed with 60% of mature trees planted in Phases 1 and 2, creating a striking green space along the waterfront.
? Internal road infrastructure: 100% asphalt and paving completion in Phase 1; Phases 2 and 3 are currently under construction and finishing.
? External infrastructure: Asphalt completed from Phuoc Thien Road to Project Gate 1; the entire Phuoc Thien Road is expected to be completed by the end of March 2025, establishing comprehensive infrastructure for the surrounding area.
Beyond accelerating construction, The Rivus continues to invest in and maintain its landscaping and green spaces with meticulous care. All construction activities are being expedited to complete premium green environments ahead of handover to future residents.
Explore the latest construction progress images of The Rivus and discover the distinction this premier villa community offers.